Sitework & utilities bid leveling
Comparing 3 bids for sitework & utilities on the Downtown Transit Hub. No coverage gaps here — all three bids cover the full scope. One extracted field is still below the confidence threshold and needs your confirmation before the total is final.
Recommended bidder
Delta Grading Co.
All three bids cover the complete scope — there are no coverage gaps on this package. Delta Grading Co. is the lowest total once its one flagged field (utility trenching) is confirmed against the source PDF.
$547,550
adjusted comparison total
3
Bidders received
5
Scope lines compared
0
Coverage gaps flagged
1
Fields need your confirmation
Lowest confirmed price on line Coverage gap — scope missing or excluded Awaiting your confirmation
| Scope line | Titan Sitework LLC $549,200 | Continental Earthworks $550,200 | Delta Grading Co. $547,550 headline |
|---|---|---|---|
| Mobilization & site setup | $42,000 | $45,500 | $43,800 |
| Excavation & mass grading | $218,000 | $205,400 | $211,900 |
| Utility trenching & backfill (storm/sewer/water) | $164,500 | $171,200 | $168,000 76% |
| Erosion & sediment control | $28,400 | $26,900 | $29,100 |
| Final grading, paving & seeding | $96,300 | $101,200 | $94,750 |