Mechanical bid leveling

Comparing 4 bids for the mechanical scope on Riverside Medical Center — Tower B. Prices come straight from each quote PDF; anything below the confidence threshold is flagged below for you to confirm before it counts toward a total.

Recommended bidder
Apex Mechanical Group

Metro Mechanical's headline price is $161,400 lower, but once its two coverage gaps (duct insulation, controls scope) are normalized to the package median, Apex is the lower true cost. Adjustment method: gap value set to the median of confirmed bidders on that line.

$1,942,000
adjusted comparison total
4
Bidders received
8
Scope lines compared
2
Coverage gaps flagged
3
Fields need your confirmation
Lowest confirmed price on line Coverage gap — scope missing or excluded Awaiting your confirmation
Scope line
Apex Mechanical
$1,942,000
Coastal HVAC Co.
$2,015,300
Precision Air Systems
$1,989,750
Metro Mechanical Group
$1,780,900 headline
Sheet metal ductwork & distribution
$412,000
$438,500
$421,900
$405,300
Duct insulation (mineral wool, R-6)
$146,200
$139,800
$151,000
Not included
Est. value $148,500 — normalized in adjusted total
Air handling units (AHU-1 – AHU-4)
$518,400
$524,000
$497,600
71%
$509,250
VRF condensing units & piping
$287,000
$291,450
$279,900
$266,800
Building automation controls (BAS integration)
$164,900
$171,200
$168,450
Excluded — see qualifier
"Controls by others," p.3 — est. value $75,000
Testing, adjusting & balancing (TAB)
$34,750
82%
$37,200
$36,000
$35,900
Permits & inspection coordination
$18,500
$19,900
$17,750
$16,200
Mobilization & general conditions
$60,250
$58,200
64%
$61,400